Repairs and re-covering: the limits
You don’t normally need to make a building control application to repair or re-cover a pitched or flat roof if:
- less than 50% of the roof is affected, and
- less than 25% of the whole building’s outer shell (walls, floor, roof, windows, doors, roof windows and rooflights) is affected.
02
When you do need approval
- The work goes over either of those limits.
- The roof structure is altered.
- The new covering would perform significantly differently from the old one in a fire.
- The new covering is 15% or more heavier than the old one.
03
Replacing the whole roof
The Planning Portal says most re-roofing of an existing building needs building regulations approval. If you’re changing material, for example from slate to tiles, approval is likely to be needed so that the roof structure can take the new weight and the roof meets fire safety and energy efficiency rules. If the new covering is a lot heavier or lighter, the structure may need strengthening, so get a structural engineer or surveyor to check it first.
04
Insulation
A roof counts as a “thermal element”, so re-covering it should include improving its insulation. This often comes up with flat roofs: if a flat roof with built-in insulation is replaced, the insulation may need upgrading.
05
Who deals with building control
Approval can come from the council’s building control team. Roofers registered with a competent person scheme can self-certify their own work instead. If your job needs building control, we’ll tell you at the quote stage. If your home is in a conservation area, you’ll need to handle the building control notification yourself.
Keep the completion certificate. When you sell the house, your buyer’s solicitor may ask for it.
06
Planning permission is separate
Building regulations are about safety and energy efficiency. Planning permission is about how the house looks. Like-for-like re-roofing usually counts as permitted development, but conservation areas, Article 4 directions and listed buildings can change that. See our Guide – Roofing in Harpenden Conservation Area.
07
Frequently asked questions
Do I need building control to replace a few tiles?
Usually not, as long as you stay under the limits above and don’t change the structure or the type of covering.
Do I need it for a new flat roof on my extension?
If you’re replacing more than half of the roof, or the insulation is being replaced, you’ll normally need approval and better insulation.
08
Planning a new roof?
See our New Roofs page, or get in touch and we’ll tell you what applies to your job.